House Project Week 22
This week the trim was installed, sanded and was started to get painted, closet door by front door was installed, plumbing work was completed,
Saturday
These images show the trim was installed. Kind of hard to see because it blends in with the wall.
Next two images show lights were installed in the dining room/living room/kitchen.
Closet door was installed next to the front door.
Monday
They made a mistake and had to redo some of the window trim again because they forgot to install the windowsills.
Tuesday
Wednesday
The dishwasher was installed.
Kitchen faucet was installed.
Toilet in secondary bathroom was installed (can't use it yet though, still no power to the house, more on this later*)
Faucet for sink and tub plumbing was installed in the secondary bathroom.
Trim was completed going down the stairs to the garage.
Master bathroom sink faucet installed.
Toilet in master bathroom was installed (can't use it yet though, still no power to the house, more on this later*)
Thursday
No images this day, mostly sanding work on trim was done. Not that much changed.
Friday
Trim was painted around this window in the master bedroom.
And this window as well.
Trim in hallway was painted.
Trim was painted in master bathroom.
Trim was painted in master bedroom closet.
Trim was painted around the door to the master bedroom.
This Week: Continue painting the trim, any other things that need to get done.
* Had a little setback with the electricity, looks like we need a transformer. Electricity will not be turned on to the house until late January, even with this setback, we are still on track to be completed on schedule.