House Project Week 15
This week the house was wrapped with siding wrap, the trim and siding were delivered, and the dry board was delivered and installed.
Monday
New door frame. The other one was the wrong size.
The floor had paper taped down to protect it and the mud and tape was delivered for the dry wall.
Looking out of the Windows of the new house
Living Room Window (looking towards Tomlins side of the house, Driveway Side of the house).
Living Room Window (looking towards Tomlins side of the house, Driveway Side of the house).
Dining Room Window (Looking towards the back of the property)
Secondary Bedroom Window (Looking Towards the neighbor's yard non-driveway side of the property)
Master Bedroom Window (Looking Towards the other house)
Master Bedroom Window (Looking Towards the neighbor's yard non-driveway side of the property)
Tuesday
First two images show survey markings (A water meter will be put in place here on Monday).
Work on the drywall has started (Mud and taping (covering up the nails that were used to put the drywall up).
Wednesday
More work on the drywall was completed (These pictures turned out great because they were all taken in the dark, workers left after 7:30pm).
This Week: Continue the drywall and maybe get the siding done if the siding wrap is all set to go.