House Project Week 19
This week painting was completed, the front stairs were built, garage door was installed and work on the floor was started.
Saturday
The flooring was started in the living room and the hallway. Almost all the rooms will have this flooring besides the bathrooms and laundry room.
Here is the backside of the garage door.
Monday
The white lines indicate where the gravel will go for a gravel pathway from the driveway to the side garage door and or house,
Tuesday
The cabinets were delivered this week and are slowly being installed moved to their proper location.
Wednesday
The gutters were delivered and installed. They are the same color as the trim.
The bathroom and laundry room floor was installed.
The cabinets were put in place in the two bathrooms.
Thursday
Friday
The gravel was laid down and now it's less muddy walking from our house to that house. Less mud to track in the new house.
The secondary bedroom floor was started.
This Week: Continue work on the floor, and get some of the cabinets installed.
To Be Determined: At some point the electrical will be turned on (didn't happen this past week)
Comments
Post a Comment