House Project Week 17

  This week painting was started on the inside and the outside of the house. The outside of the house is starting to match the main house and the garage. 

                                                                      Saturday

Work was started on the front stairs.

Monday
The garage was boarded up to protect it from the elements.

   Tuesday





Painting was started on the siding. The siding now matches the garage and the main house. 

Wednesday

Painting is going on inside of the house too. (This images are taken outside looking through a couple of windows, can't go in the house for now, the floor was a mess).

Thursday



The siding was completed. (This is one white house). 

Some forms for the front stairs. 

This door now has some door hardware (A lock). 

Friday






The trim and the roof overhangs were getting painted blue. Now the house is starting to look very familiar. 

This Week: Continue and finish painting, start work on the floor and get the house prep for when accessories come (like cabinets for example). Sounds like in a couple of weeks the cabinets for the kitchen and the island will come. 