House Project Week 16

 This week more work was done on the drywall, siding, trim were completed and the two porches were completed as well. 

                                                                      Monday



The water meter was installed. This was where the big green pipe was. See image below.


   Tuesday













The trim was installed around all the exterior doors, windows, porches and power box. 

Wednesday



Work was started on the siding (by the front door and the back of the house) and putting trex deck on the front and back porch. 

Thursday







More work was done on the siding (all around the garage was done, most of the siding that we can see from out kitchen window as almost done, and the arborvitae side of the house). 

Friday
More trim was delivered (This is the trim for the inside of the house). 








The siding and the two porches are all done.

This Weekend: Pick out paint colors, garage door, countertops for the kitchen and bathrooms, flooring for the house (which is already picked out) and front cabinet colors. Instead of telling you the decisions next week, I will post pictures of then there are getting installed to give you all a better idea.    
This Week: Finish drywall, then start flooring (Which should be coming this week), and maybe start painting the interior or exterior of the house. 

Comments

Popular posts from this blog

House Project Week 15

House Project Week 39

House Project Week 42