House Project Week 14
This week the house was wrapped with siding wrap, the trim and siding were delivered, and the dry board was delivered and installed.
Monday
This is what goes between the plywood and the siding. It helps to protect the house from rain (water)
Wednesday
The dry board was delivered and was left in each of the bigger rooms and the hallway.
Gravel was also delivered.
The gravel was placed under the deck so that weeds cannot grow under the deck.
A New hose faucet was installed as well.
The entrance to the crawl space was fixed the other entrance was the wrong size.
Thursday
First two images garage. With door leading to a staircase that leads into the house.
Stairs going from garage to house (hallway)
Master Bedroom
Master Bedroom
Master Bedroom Bathroom
Master Bedroom Bathroom and Closet
Secondary Bedroom
Secondary Bedroom Closet
Living Room Closet and Front Door
Kitchen
Dining Room
Ceiling
The dry board was installed, and you can really see how the rooms will look. You can now see some closets taking shape as well. This Week: Hopefully get the siding and the trim started and maybe get more work on the dry wall as well.