House Project Week 14
This week the house was wrapped with siding wrap, the trim and siding were delivered, and the dry board was delivered and installed. Monday This is what goes between the plywood and the siding. It helps to protect the house from rain (water) Wednesday The dry board was delivered and was left in each of the bigger rooms and the hallway. Gravel was also delivered. The gravel was placed under the deck so that weeds cannot grow under the deck. A New hose faucet was installed as well. The entrance to the crawl space was fixed the other entrance was the wrong size. Thursday First two images garage. With door leading t...