Driveway Week 3
Driveway Week 3
This week the driveway poject continued. More prep work was done on the driveway plus some landscaping was done as well.
Sunday
Monday
Gravel was laid down as the first step to making the new driveway. With the gravel now, it marks where the new driveway will be now.
Wednesday
They dug more by the road and this time made a connection to the water pipes. This green pipe is the marker where the water meter will go once the new house is built on the new property.Friday
Landscaping was started on Friday and will contunie at somepoint. Couldn't find all the plants that we wanted.
Upcoming
This Week: Hopefully finish the driveway this week and wrap this part of the project up.
Couple of Weeks: We have someone lined up to do the sidewalk (concerte) that will connect the patio to the garage and driveway.
Hopefully Soon: Start work on the fence. Dad met with fence people this past week and currently waiting for estimates.