 Week Two Update

This week, the concrete was poured and the structure of the garage was established as well.  

Tuesday




The Concrete was laid down. This shows how much higher the road will be to match up with the floor of the garage.  

Wednesday





They took the forms out and laid dirt around the foundation so they could walk up as close as they want and not fall into any holes.

Thursday






Here is the structure of the garage. It's very similar to the one garage with a couple of differences, one its turned 90 degrees and 2nd it doesn't have the small lean-to in the back, so we gain some space in the back of the garage. 

And Now for a Added Bonus 



They also dug a trench on Thursday as well, they need to put some pipes down here as well. 

Upcoming

This week: Siding, roofing and painting will be started plus the side garage door not the overhang door will be installed as well.  .

Will post another update next weekend about week 3 progress.  